CBAM actual emissions vs default values for fasteners
Default values carry a mark-up; verified actual data does not, and its deduction is based on the steel you actually use. For the same CN code the two paths can differ by an order of magnitude.
- 7318 15 82, Q3 2026: €467.79/t on default values; €47.57/t on the Commission example plant's actual data.
- Actual data must be verified by an accredited CBAM verifier; otherwise default values apply.
- EAF steel only pays off on the actual-data path; the default path still deducts (C).
- The example plant is fictitious and illustrates the method only.
1. One CN code, two paths
| Default path | Actual path (Commission example 3) | |
|---|---|---|
| Embedded emissions per t | 6.375 × 1.10 = 7.0125 | 2.039 (example plant, table 4-13) |
| Deduction (SEFA × 0.975) | 1.364 × 0.975 = 1.3299 | (0.038 + 1.176 × 1.242) × 0.975 = 1.4611 |
| Certificates per t | 5.6826 | 0.5779 |
| × Q3 price €82.32 | €467.79 | €47.57 |
Example 3 is actually CN 7318 12 90 (carbon-steel wood screws). It shares the 0.038 column-A benchmark and the method with 7318 15 82, so we use it for comparison. The plant is fictitious.
2. Where the gap comes from
- Mark-up: default values reflect the exporting country's average intensity plus 10% (20% in 2027, 30% from 2028). The Commission Q&A says the marked-up values are set so emissions are not underestimated, so actual values should in most cases be more advantageous.
- Different deduction: the default path deducts the whole-chain column-B benchmark; the actual path deducts the column-A process benchmark plus steel use × the precursor's SEFA.
- Steel dominates: in the Commission example the steel precursor is about 90% of the bolt's emissions (1.843 ÷ 2.039).
3. EAF steel only helps on actual data
Assume scrap-EAF wire rod with steel emissions of 0.5 or 1.0 tCO₂/t (assumed range), steel use 1.176, own processing ignored, precursor SEFA estimated at 0.066 (column B (E), the calculator's estimate):
| Steel emissions (assumed) | Embedded per t | Certificates per t | Cost per t (€82.32) |
|---|---|---|---|
| 0.5 | 0.588 | 0.4753 | €39.12 |
| 1.0 | 1.176 | 1.0633 | €87.53 |
Without verified data the same EAF supplier is back at €467.79/t on default values. The real precursor SEFA comes from the mill's verified report; the table shows orders of magnitude only.
4. What the actual path needs
- Own-plant and purchased-steel emissions in the Commission operator template (iron and steel: direct emissions only).
- Mill (precursor) actual emissions and SEFA; where missing, marked-up default values.
- Verification by an accredited verifier. The Commission's state of play of 9 Nov 2026 shows 7 of 24 participating national accreditation bodies have agreed and are accepting applications from third-country verifiers – capacity is tight.
- Verified data handed to the EU importer for the declaration.
5. Is it worth it?
Saving per tonne × EU tonnage per year, against verification and data costs. On the example figures the gap for 7318 15 82 is about €420.22 per tonne – €42,022 on 100 tonnes. Your own figure needs your own steel data.
Official sources
- European Commission – Guidance No. 5d: iron and steel (14 Aug 2026; example 3, tables 4-12 to 4-14)
- European Commission – Guidance No. 4: free allocation adjustment (14 Aug 2026; CBAM factor Table 2-1, section 2.2.1.2)
- European Commission – Guidance No. 3: methods for calculating embedded emissions (14 Aug 2026; mark-ups 10/20/30%)
- European Commission – CBAM default values, v2 Excel (6 Aug 2026, correcting Implementing Regulation (EU) 2025/2621 via 2026/1740)
- European Commission – CBAM benchmarks Excel (Implementing Regulation (EU) 2025/2620, Annex point 5)
- European Commission – Price of CBAM certificates
- European Commission – Verification of CBAM emissions
- European Commission – CBAM Questions and Answers (Q 4.25 default values and mark-ups)
Related guides
- CBAM default values for CN 7318 fasteners from China, and the 2026 cost per tonne
- CBAM certificate price 2026: the official quarterly prices and how to use them
- CBAM for steel structures (CN 7308): how the cost is calculated
- CBAM 7326: China default values and cost per tonne
- CBAM free allocation adjustment: benchmarks, CBAM factor and CSCF
- CBAM 50-tonne threshold and the 2027 timeline