For China, the default value for 7308 is set once at 4-digit level – 6.035 tCO₂/t for every 7308 subheading. The method is the same as for fasteners; the benchmark is different.

Key points
  • China 7308 default value 6.035 (route (C)); 6.639 including the 2026 mark-up.
  • Column-B benchmark (C) 1.491; 5.1848 certificates per tonne in 2026.
  • At the Q3 price of €82.32: €426.81 per tonne; at Q1/Q2 prices about €390.72/€390.31.
  • EU imports of 7308 from China, Jan–Aug 2026: 970,953 t, +19% year on year (Eurostat).

1. What 7308 covers

Heading 7308 covers structures and parts of structures of iron or steel: bridges (7308 10), towers and lattice masts (7308 20), doors and windows and their frames (7308 30), scaffolding and propping equipment (7308 40), panels and other structures (7308 90). Steel solar mounting and racking are often classified under 7308 90 or 7326; confirm your CN code with your customs broker. 7308 is in the iron and steel list of Annex I to Regulation (EU) 2023/956.

2. Default path, step by step (1 t, imported Q3 2026)

  1. China 7308 default value 6.035, plus 10% → 6.6385
  2. Column-B benchmark (C) 1.491 × 0.975 × CSCF 1.0 = 1.4537
  3. Certificates per tonne: 6.6385 − 1.4537 = 5.1848
  4. × €82.32 = €426.81 per tonne
CaseCost per tonne
Imported Q1 2026 (€75.36)€390.72
Imported Q2 2026 (€75.28)€390.31
Imported Q3 2026 (€82.32)€426.81
Imported 2027 (20% mark-up, factor 0.950; price assumed €82.32)€479.56

A 500-tonne project imported in Q3 is €213,405 on default values.

3. Actual-data path: a teaching example (assumed values)

There is no Commission example plant for 7308, so this is an explicitly assumed example: steel use 1.05 t/t (assumed); steel precursor 1.567 tCO₂/t and precursor SEFA 1.242 from the carbon-steel bars in Guidance 5d example 1; own welding and galvanising fuel 0.05 (assumed).

  1. Actual emissions 1.05 × 1.567 + 0.05 ≈ 1.695
  2. Deduction (column A 0.112 + 1.05 × 1.242) × 0.975 = 1.3807
  3. 0.3143 certificates × €82.32 = €25.87 per tonne

This is not any real plant. It shows the structure: the bulk of a steel structure's emissions sits in the purchased steel, so verified mill data decides whether you can leave default values.

4. The 7308 problem: mixed mills

One project often uses plate and sections from several mills and furnace types. On actual data, each batch's embedded emissions must be matched to its mill. Steel without data can only enter as a (marked-up) default precursor value.

5. Trade volume

Eurostat Comext (DS-045409, updated 16 Oct 2026): EU imports of 7308 from China in Jan–Aug 2026 were 970,953 t, +19% year on year, 51% of extra-EU volume, worth about €1,680.7m.

Official sources

  1. European Commission – CBAM default values, v2 Excel (6 Aug 2026, correcting Implementing Regulation (EU) 2025/2621 via 2026/1740)
  2. European Commission – CBAM benchmarks Excel (Implementing Regulation (EU) 2025/2620, Annex point 5)
  3. European Commission – Guidance No. 4: free allocation adjustment (14 Aug 2026; CBAM factor Table 2-1, section 2.2.1.2)
  4. European Commission – Guidance No. 5d: iron and steel (14 Aug 2026; example 3, tables 4-12 to 4-14)
  5. European Commission – Price of CBAM certificates
  6. Eurostat Comext – EU trade by CN8 (dataset DS-045409, updated 16 Oct 2026)
  7. European Commission – CBAM legislation and guidance